How much waste should I allow when ordering stock?
Don't add a flat percentage. Work out the cutting plan first, order the bars it uses, and add a spare only as cover for a miscut. A 10% or 15% allowance is a guess about how well the parts will pack, and the real waste depends entirely on the cut list: 2.9% on one job below, 25% on the other. A flat allowance buys steel you don't need on the first and leaves you a bar short on the second.
Job 1: the allowance over-orders
140 parts from 6000 mm bars with a 3 mm blade: 40 at 2600 mm, 40 at 1650 mm and 60 at 1050 mm. That is 233000 mm of parts.
| How the order was worked out | Bars ordered |
|---|---|
| Parts + 10% | 43 |
| Parts + 15% | 45 |
| Optimised cutting plan | 40 |
The plan cuts every part from 40 bars and is proved optimal: 20 bars cut 2600 + 1650 + 1650, and 20 cut 2600 + 1050 + 1050 + 1050. 2.9% of the steel bought is left over. The 10% rule buys 3 bars, 18 metres, that go straight onto the rack. The 15% rule buys 5.
Job 2: the allowance under-orders
Twelve parts from the same 6000 mm bars: six at 3100 mm and six at 1400 mm. That is 27000 mm of parts; add 10% and you get 29700 mm, which is 5 bars.
It takes 6. Two 3100s plus the cut come to 6203 mm, so no bar holds two of them, and every 3100 needs a bar of its own. The optimiser's plan is six bars of 3100 + 1400, leaving 1494 mm on each: 25% of the steel bought. Order on the 10% rule and you are a bar short with the saw running.
Where an allowance still belongs
Allowances are for what the plan cannot see: a miscut, a bar that arrives bent or short, rough ends that need squaring. Those are per-bar risks, so cover them per bar: a spare bar for the miscut, and the trim setting, which takes a blade width off both ends of every bar, for the ends. Put them on top of a real plan, not in place of one.
FAQ
Is 10% a good waste allowance?
Does the waste figure include the saw blade?
Is the leftover waste, or stock?
How do I order when the supplier has several lengths?
Run your own cut list
The calculator is free, needs no account and takes up to 500 parts a job. It allows for the blade, uses your offcuts, and tells you when the plan is proved optimal.